top of page
Cropped Logo1.png

Case Studies

Please see projects that have used LovEnergy's SaaS and associated services

Building to Grid NYC Manhattan

Problem: How to avoid Local Law 97 penalties and therefore go green for a Multi Family Apartments in NYC in a cost-effective manner?

 

 

Solution: Used LE software to model and simulate the multi story multi family apartments as is and with a suite of potential clean energy investments to determine costs and benefits.

 

Results: The following potential clean energy investments were studied, with CHP, Battery storage, space and district hot boiler replacements identified as the only investments with positive NPV, after factoring in grid side interconnection and programs:

 

•Insulation

•LEDs

•Solar PV

•Battery Storage

•CHP

•Plug load reduction

•Gas boiler replacement

•Heating radiator Improvements

•Window replacement

•ASHP

image.png
image.png

Green Factory

Problem Statement:  A large 10 MW factory in New Mexico had decided to make clean energy investments to meet Science Based Targets (net zero energy consumption) but with no changes to factory operations The company didn’t know what investments to make nor costs and benefits thereof

 

 

Solution: LovEnergy conducted a techno-economic feasibility study to assess several potential clean energy investments including solar, wind and energy storage. The study evaluated hourly loads over a 10 year period to understand the energy needs to be offset by the clean investments. Subsequently the capacity, costs and benefits of solar and wind requirements were determined and potential interconnection issues identified. Boundary conditions such as target operation date and land availability were factored. 

​

Results: The study determined none of the scenarios analyzed hadbenefits exceed the costs, yet the net zero goal could be achieved but unlikely to meet the desired target operational date due to current interconnection queue challenges.

 

47 MW of Wind energy met the net zero goal and had the best of the worst BCR (Benefit Cost Ratio) of 0.72, however there isn't sufficient land available at the site. 70 MW of Solar PV also meets the net zero goal but requires LI-ION battery storage of 33 MW and 348 MWh to obtain a better BCR of 0.67 than 0.46 without storage.

Both negative and positive impacts to transmission lines were identified that could result in the company having to pay towards grid upgrades despite the positive impact to some lines.
 

Puerto Rico Recreation Center

Problem: Identify the optimal clean energy investments for a recreation center in Puerto Rico

​

Solution: The LovEnergy software was used to model and simulate the impacts of making clean energy investments at a recreation center in San Juan using publicly available data.

 

The following clean energy technologies were studied:

 

•Insulation

•LEDs

•Solar PV

•Energy Storage

•Energy efficient appliances

•Window replacement

•Ground source heat pump

•EV charging stations

​

Results:  The results revealed a (pre-EV and storage installation) reduction of electrical energy consumption of 74% and 100% gas consumption and a 54% reduction in electrical peak load, furthermore becoming a net exporter of electrical energy to the grid

 

 

•Proposed clean energy investments modeled reveals:

• ~ 93% increase in electrical peak load due to new EV charging load

• 100% reduction in gas peak due to GSHP  

• ~80% increase in electrical energy consumption due to new EV charging load

• ~53% net reduction of utility import despite new EV charging load, due to solar PV

 

 

•Adding a 103 kW and 627 kWh battery storage, plus managed EV charging, enables a shift of peak electrical load from day time peak to night time helping reduce grid constraints and potential grid upgrade costs

image.png
bottom of page